Эротические рассказы

. Читать онлайн книгу.

 -


Скачать книгу
then be able to identify the general format and construction of the specification manual. In turn, you will be able to target those issues that have the most impact on your work.

      The project specifications begin with Division 00—Procurement and Contracting Requirements. This division indicates the qualifications that must be met by the contractors bidding the job.

      The rules that govern the completion of the work are in the General Requirements or General Conditions, which explain everything with regard to the information of the architect and engineers of record, the project location, the bid invitation, the instruction of bidders, the execution of the contract (including first billing information through to the final terms), and conditions of contract close out.

      Following the general conditions, the specification book is broken down by construction divisions relative to the specific trades. Sections within these divisions identify the different types of work to be performed by each individual trade.

      Table 4.1 Divisions of Sample Specifications

Division 1—General Conditions
Division 2—Site Work
Division 3—Concrete
Division 5—Metals
Division 6—Wood and Plastics
Division 7—Thermal and Moisture Protection
Division 8—Doors and Windows
Division 9—Finishes
Division 10—Specialties
Division 11—Equipment
Division 12—Furnishings
Division 13—Pre-Engineered Structures
Division 15—Mechanical
Division 16—Electrical

       Note that there are no Divisions 4 and 14; these are held for cases where special reference might be needed. Generally the rest of the numbered divisions remain the same.

       Sample Project Specifications

      The steel fabricator’s scope of work is always defined within the project specifications as Division 05—Metals. This division contains all the information for those construction items related to steel. Sections for structural steel, miscellaneous steel, steel joist, steel deck, architectural metals, steel stairs, grating, and railing are found in Division 5. Generally anything that is metal will be included in this division.

      The sections in Division 5 are numbered. For example, Section 051200 Structural Steel and Section 055000 Miscellaneous Steel list some of the major components that the designer intends you (steel estimator) to supply as part of your package. Check any other sections within Division 5 for which your company is supplying materials.

      Be aware that designers are not consistent about how they construct the sections for Division 5 items. For example, steel stairs and rails generally are included in the 055000 Miscellaneous Metals, but sometimes they may have their own designated sections. The decision to provide a separate subsection for certain fabricated items tends to be at the whim of the designers; it may be based on the quantity of the individual items to be fabricated. For example, if there is not much to be fabricated in the way of steel stairs and railing, then the guide for fabricating them would be included in the section for miscellaneous metals. If there is a significant amount of this work to be performed, however, then the designers would create a separate subsection for stairs and another one for handrail.

image image

      Read through the specifications carefully. Be sure you comprehend the information as the writer intended. When in doubt, ask questions—whether of a work colleague, the customer, or the general contractor. You can also call the architect or engineer to be sure you get a correct interpretation. It is always good to obtain these clarifications in writing.

      Figure 4.1 shows a typical description of the items found in Section 051200—Structural Steel. Figure 4.2 then shows a sample of Section 055000—Metal Fabrications. Typical headings are shown as examples, followed by explanation of the items in italics.

      References to other trades often occur within Division 5. An example is the common reference to Section 099000 for Paint and Painting. The reference to Section 099000 for Paint and Painting may be necessary to direct your attention to the specific painting or galvanizing requirement that will apply to the fabricated steel. When you find these references, read them carefully so that you will be aware of any labor or material cost impacts to your pricing.

      You must be aware of any references to other trades and make them clear to others in your bid letter’s provisions.

      If the steel fabricator fails to specifically address whether these sections are included or excluded in the bid letter, the contractors bidding this project will assume by your omission that you are including all items in your Division. Therefore, the steel fabricator could end up being required to provide or supply items that were not priced in the quote.

      These sections are written as guides; much of the information may be borrowed from other similar projects. Sometimes the information given may not apply to the job you are bidding. Know that the specifications will list items both generally and specifically. Therefore, you must ferret out from the set of contract drawings all of the structural and miscellaneous steel items to be fabricated. Then be clear and concise about your provisions in the scope letter with the quoted price.

      While working on the take off, steel estimators become aware of what is and is not being used in the specifications. Items that do not apply to their scope of work are listed at the exclusions in the bid letter to the customer. Prior to the bid date, it is good to provide a scope letter to the general contractor prior for their review. You can then bring to their attention any issues that you see within the scope of work and come to an early resolution of those issues. Unanswered questions may cause you to add extra money to the bid price to cover the unknown. To assure you are providing a competitive bid, clear up these issues early.

      If the project is smaller, the specifications may not be broken down by divisions. Still, there will be some information provided in the project specifications as to what the designer expects you to provide.

      If no information is provided for the steel fabricator in the way of specifications, any standard set of specifications may be used as a guide to help with what should be included or excluded with the quote.

      If you have difficulty finding information on the contract drawings and specifications, you can always call the architect or engineer who created the documents. Sometimes details are not shown where they should be, or more clarification is needed for a certain condition in the drawings.

      Discovery of missing information or mistakes within the bidding specifications and drawings that the architect and engineer have released will create an Addendum—a revision to the


Скачать книгу
Яндекс.Метрика